Analisis Produktivitas Alat Berat Pada Konstruksi Jalan Sewan Munukania, Papua

Authors

  • Aryaditya Wisnu Mangarso universitas katolik widya karya malang
  • Lila Khamelda Universitas Katolik Widya Karya Malang
  • Sunik Universitas Katolik Widya Karya Malang

Keywords:

Excavator, Dump Truck, Motor Grader, Vibro Roller, Truck Mixer, Asphalt Finisher, CTB

Abstract

The subgrade work and road pavement layer work carried out in the Sewan Munukania road project, Petam Village, South Sarmi District, Papua, were performed 14.900 km with a road width of 8 m. The analysis was conducted on the performance of heavy equipment used in the subgrade and pavement layer works in the Sewan Munukania road project. The results showed that the heavy equipment productivity for excavation work of 225 m³ used 1 excavator with a productivity of 1,519.672 m³/day and a duration of 0.14 days, while 3 dump trucks achieved 345.03 m³/day with a duration of 0.65 days. Coral fill work of 644.25 m³ used 1 excavator with a productivity of 736.75 m³/day and a duration of 0.87 days, 3 dump trucks with 7.89 m³/day in 3.88 days, 1 motor grader with 1,628.57 m³/day in 0.05 days, and 1 vibro roller with 73.45 m³/day in 1.21 days. Sand fill work of 4.56 m³ used 1 excavator with a productivity of 1,150 m³/day and a duration of 0.003 days, 3 dump trucks with 43.15 m³/day in 0.005 days, 1 motor grader with 1,680 m³/day in 0.0003 days, and 1 vibro roller with 112.84 m³/day in 0.005 days. The subbase layer work of 11,920 m³ used 1 excavator with a productivity of 105.25 m³/day in 16.17 days, 3 dump trucks with 7.89 m³/day in 71.94 days, 1 motor grader with 244.28 m³/day in 6.97 days, and 1 vibro roller with 528.15 m³/day in 22.56 days. The base layer work of 35,760 m³ used 1 truck mixer with a productivity of 44.59 m³/day in 801.97 days. The surface layer of 2,384 m³ used an asphalt finisher with a productivity of 267.19 m³/day in 8.9 days, and a tandem roller with 34.23 m³/day in 6.54 days.

References

Adatika. (2006). Pekerjaan Tanah dasar. http://eprints.undip.ac.id/34707/3/ 1709_CHAPTER_I.pdf

Astutie, C. S. A. (2018). Dumptruc. 1–26.

Clarkson H. Oglesby, 1999. (1999). Definisi Jalan. Jalan Raya, 4(1), 1–23.

Darlan. (2014). Konstruksi Perkerasan Lentur (Flexible Pavement). 23 July 2014.

Direktorat Jenderal Bina Marga. (2018). Spesifikasi umum 2018. September. https://doi.org/10.1016/j.clnu.2012.07.008

Ervianto W.I. (2005). Produktivitas Tenaga Kerja Dengan Metode Work Sampling, Yanti G.

Global, S. (2001). Motor Grader (Vol. 6, p. 40).

Hardiyatmo. (2007). Lapis pondasi bawah. Http://E-Journal.Uajy.Ac.Id/7244/4/3TF03686.Pdf, C, 15–48.

Heavy Equiment Management, N. S. (2014). II-1. http://www.senyawa.com

Kementrian PUPR Spesifikasi Pekerjaan Tanah. (2016). Diklat Spesifkasi Umum Spesifikasi Pekerjaan Tanah 2016 Modul 4 Kementerian Pekerjaan Umum Dan Perumahan Rakyat Badan Pengembangan Sumber Daya Manusia.

Komalasari, M., Fardila, D., Dharmawansyah, D., & Kurniati, E. (2023). Analisis Produktivitas Alat Berat dan Pekerja di Pekerjaan Pengecoran Lantai Spillway pada Proyek Pembangunan Bendungan. 17(03). https://doi.org/10.21776/ub.rekayasasipil.2023.017.03.5

Kosanke, R. M. (2019). Pengertian, Tipe dan Penggunaan Excavator. 5–22.

Kusuma, D. (2014). Jalan 2.

Mangarso, A. W. (2022). Laporan Praktek Kerja Nyata Program Studi Teknik Sipil Fakultas Teknik Universitas Katolik Widya Karya Malang 2022.

Nugroho, M. (2003). Bab iii landasan teori 3.1. Http://E-Journal.Uajy.Ac.Id/ 7244/4/3TF03686. Pdf, C, 15–48.

Peraturan Menteri Pekerjaan Umum No. 11/PRT/M/. (2013). Peraturan Menteri Pekerjaan Umum Republik Indonesia.

Permen PUPR No. 28. (2016). Permen_PUPR_No 16.

PT Citra Karya Papua. (2022a). Uraian analisa 2 alat berdasarkan 1 HPS Peningkatan Jalan Lingkar Petam-Pertigaan Sewan Munukania _Skripsi. 30.

PT Citra Karya Papua. (2022b). Uraian analisa alat berdasarkan 1 HPS Peningkatan Jalan Lingkar Petam-Pertigaan Sewan Munukania _Skripsi. 30.

Rohman. (2003). BAB II TINJAUAN PUSTAKA 2.1 Tinjauan Umum.

Rostiyanti. (2002). 3. BAB III.

Rostiyanti. (2008). Analisa Produktivitas Alat Berat Dalam Pekerjaan Penghamparan Material Agregat Pada Proyek Pembangunan Jalan Tol Pekanbaru-Padang Seksi Vi Pekanbaru-Bangkinang.

Sentrakalibrasiindustri. (2023). excavator.

Simbolon, J. M. (2021). Analisis Produktivitas Dan Biaya Penggunaan Alat Berat Pada Pelaksanaan Pekerjaan Lapisan Perkerasan Lentur.

Sinambela. (2020). Jenis prancanaan Kuantitatif.

Sokop, R. M., Arsjad, T. T., & Malingkas, G. (2018). Analisa Perhitungan Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea.

Suhendra, A. R. (2022). Analisa Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Proyek Rehabilitasi Jaringan Irigasi D.I Jurang Batu Kabupaten Lombok Tengah.

Sukirman. (1992). Perkerasan kontruksi jalan. 5–20.

Sulistyan Nizar, H. (2016). Rancang Bangun Simulasi Compactor Dengan Sistem Mekanis (Proses Pengujian). 1–23.

TREK. (2016). vibra. https://www.google.com/imgres?q=vibratoryroller&imgurl=https%3A% 2F%2Fassets-global.websitefiles.com%2F5cfe470c04ff07a25ad08aec%2F5d5b969fe5ce73a3cc 6378b7_sv512d.png&imgrefurl=https%3A%2F%2Fwww.trek.id%2Fvibroroller%2Fsakai-sv512 d&docid=HOAzDFp3Nh1ChM&t

Umar, H. (2013). Metode Penulisan Laporan KKP, Yuniati Ulfa 2021. Angewandte Chemie International Edition, 6(11), 951–952., 2013–2015.

Wigroho. (1982). Estimasi Penggunaan Alat Berat Pada Pekerjaan Agregat Lapis Pondasi Kelas B Jalan Simpang Pertamina - Jembatan Pulau Birandang Kecamatan Kampar (Azlansyah Putra 2020).

Downloads

Published

2025-12-31

How to Cite

Wisnu Mangarso, A., Khamelda, L., & Sunik. (2025). Analisis Produktivitas Alat Berat Pada Konstruksi Jalan Sewan Munukania, Papua . Jurnal Teknik Sipil , 3(2), 01–28. Retrieved from https://ejournal.widyakarya.ac.id/index.php/Sipil/article/view/187

Similar Articles

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)

1 2 > >>